Issuance of Building Permit

About

About the Service

A Building Permit is a document issued by the Building Official to an owner/applicant to proceed with the construction, installation, addition, alteration, renovation, conversion, repair, moving, demolition or other work activity of a specific project/building/structure or portions thereof, upon the approval of the accompanying principal plans, specifications and other pertinent documents with the duly notarized application, which will be found satisfactory and substantially conforming with the National Building Code of the Philippines and its Implementing Rules and Regulations. (PD 1096)

Under Chapter 3, Sec. 301 of PD 1096, No person, firm or corporation, including any agency of the government is allowed to construct, alter, repair, convert, use, occupy, move, demolish and add any building/structure or any portion thereof or cause the same to be done, without first obtaining a building permit from the Building Official assigned in the place where the
subject building/structure is located or to be erected.

How to avail of the service and Time frame of Issuance

Steps
Follow These Steps
It Will Take You Please Approach
Client
Personnel
1 Secure Checklist of Requirements Provide checklist and give instructions 1 min. -Aldemar D. Tupas
-Heirene C. Gempasao
-Mary Ann A. Obidas
-Rizalie B. Dacules
2 Submit corresponding plans and requirements as per checklist with filled up permit forms and supporting documents Check completeness of documents attached Rest’l.-5 mins.
Comm’l.- 10 mins.
-Aldemar D. Tupas
-Heirene C. Gempasao
-Mary Ann A. Obidas
-Rizalie B. Dacules
Evaluation, assessment of Fees and signature of every section head 1 Hour Charlie S. Hinolan
Line & grade
Anthony O. Sayo
Sanitary/Plumbing
Siena Lane Tanguan
Electrical
Charry C. Cangque
Structural
Rowena Briones-Lobaton
Architectural
Robert Joy Alipalo
Mechanical
3 Payment of assessed fees to City Treasurer’s Office CTO collects payment and issue OR N/A -City Treasurer’s office personnel
4 Submit Official Receipt -Acting Building Official signs and approves the permit
-Record and release plans, documents and retain an office file
10 mins. -Aldemar D. Tupas
-Heirene C. Gempasao
-Mary Ann A. Obidas
-Rizalie B. Dacules

Document

Documentary Requirements

When applying for a building permit, submit six (6) sets of the following:
    

  1. Application Forms (Duly Accomplished)
  2. Owner’s proof of Lot Ownership
    1. Tax Declaration ( From Assessor’s Office)
    2. Land Tax Receipt ( current)
    3. Lot plan (signed and sealed by Geodetic Engineer) with attached Surveyor’s Certification
    4. Any of the following applicable:
      1. Lot Title
      2. Transfer of Certificate of Title
      3. Deed of Absolute Sale
      4. Contract to Sale ( with attached Lot Title of previous owner)
      5. Authorization to Construct (Notarized) and Lot Title of the previous owner
      6. For Barangay Site/Lot : Authorization to construct (notarized) signed by the Brgy. Captain or Certification from Mayor
      7. For Relocation Site : Certification of Award from the City Planning Office @ 2nd floor of City Hall
  3. Working Drawings (signed and sealed by duly licensed Architect or Civil engineer, Sanitary Engineer, Master Plumber , Professional Mechanical Engineer and Professional Electrical Engineer with their attached valid Prc ID, PTR and TIN).
  4. General Specification and Bill of Materials and Estimates (signed and sealed by duly licensed Architect / Civil Engineer and signed by the Lot owner or Applicant)
  5. Other Requirements (if applicable)
    1. For Construction along the National Highway: – DPWH Clearance from the DPWH Office at Matab-ang, Talisay City
    2. Fire Safety Inspection Certificate ( from the Fire Department , Quezon Street at the back of Police Station or in front of Fuentes Gas Station
    3. Locational Zoning Clearance ( from the City Planning Office at 2nd Floor, City Hall
    4. Mechanical Permit and Plan- for building with air conditioning unit exceeds the minimum required (signed and sealed by Prof’l. Mechanical Engineer)
    5. Structural Analysis (signed and sealed)– for Two Storey building and up
    6. Boring Test (signed and sealed)- for Three Storey building and up
    7. For other Buildings (e.g. Industrial Buildings ,Beach Resort, Piggery, Poultry, etc.), if applicable :
      1. Environmental Compliance Certificate (ECC) or CNC ( Certificate of Non-compliance)
      2. Neighborhood Consent
      3. SP Resolution
    8. For Cellsite:
      1. Environmental Compliance Certificate (ECC) or CNC ( Certificate of Non-compliance)
      2. Air transportation office Clearance (ATO)
      3. National Communication Commission Clearance (NTC)
      4. Neighborhood Consent
      5. SP Resolution

Fees

Fees

Pursuant to Section 203, Subsection (4) of the P.D. 1096 which authorized the Secretary of the Department of Public Works and Highways to prescribe and fix the amount of fees and other charges that the Building Official may collect in connection with the performance of its regulatory functions, the attached Schedule of Building Permit Fees and other charges is hereby promulgated to form part of the Revised Implementing Rules and Regulations of P.D. 1096, otherwise known as the National Building Code of the Philippines.

  1. Bases of assessment
    1. Character of occupancy or use of building/structure
    2. Cost of construction
    3. Floor area
    4. Height

  2. Regardless of the type of construction, the cost of construction of any building/structure for the purpose of assessing the corresponding fees shall be based on the following table:
  3. Table II.G.1. On Fixed Cost Of Construction Per Sq. Meter

    Location Group
    All Cities and Municipalities

    A, B, C, D, E, G, H, I F J
    P10,000 P8,000 P6,000

  4. Construction/addition/renovation/alteration of buildings/structures under Group/s and Sub-Divisions shall be assessed as follows:
    1. Division A-1
    2. Area in square meters Fee per square meter
      i Original complete construction up to 20.00 sq.meters P2.00
      ii Additional/renovation/alteration up to 20.00 sq. meters
      regardless of floor area of original construction
      P2.40
      iii Above 20.00 sq. meters to 50.00 sq. meters P3.40
      iv Above 50.00 sq. meters to 100.00 sq. meters P4.80
      v Above 100.00 sq. m to 150 sq. meters P6.00
      vi Above 150.00 sq. meters P7.20

      Sample Computation for Building Fee for a 75.00 sq. meters floor area:
      Floor area = 75.00 sq. meters
      Therefore area bracket is 3.a.iv.
      Fee = P 4.80/sq. meter
      Building Fee = 75.00 x 4.80 = P 360.00

    3. Division A-2
    4. Divison B-1/C-1/E-1,2,3/F-1/G-1,2,3,4,5/H-1,2,3,4/I-1 and J-1,2,3
    5. Area in ssquare meters Fee per square meter
      i Up to 5,000 P23.00
      ii Above 5,000 to 6,000 P22.00
      iii Above 6,000 to 7,000 P20.50
      iv Above 7,000 to 8,000 P19.50
      v Above 8,000 to 9,000 P18.00
      vi Above 9,000 to 10,000 P17.00
      vii Above 1,000 to 1,500 P16.00
      viii Above 15,000 to 20,000 P15.00
      ix Above 20,000 to 30,000 P14.00
      x Above 30,000 P12.00

      NOTE:Computation of the building fee for item 3.c. is cumulative. The total area is split up into sub-areas corresponding to the area bracket indicated in the Table above. Each sub-area and the fee corresponding to its area bracket are multiplied together. The building fee is the sum of the individual products as shown in the following example:

      First 5,000 sq. meters @ 23.00 P115,000.00
      Next 1,000 sq. meters @ 22.00 P22,000.00
      Next 1,000 sq. meters @ 20.50 P20, 500.00
      Next 1,000 sq. meters @ 19.50 P19,500.00
      Next 1,000 sq. meters @ 18.00 P18,000.00
      Next 1,000 sq. meters @ 17.00 P17,000.00
      Next 5,000 sq. meters @ 16.00 P80,000.00
      Next 5,000 sq. meters @ 15.00 P75,00.00
      Next 10,000 sq. meters @ 14.00 P140,000.00
      Last 2,000 sq. meters @ 12.00 P24,000.00
      Total Building Fee P531,000.00
    6. Divisions C-2/D-1, 2, 3
    7. Area in ssquare meters Fee per square meter
      i Up to 5,000 P12.00
      ii Above 5,000 to 6,000 P11.00
      iii Above 6,000 to 7,000 P10.20
      iv Above 7,000 to 8,000 P9.60
      v Above 8,000 to 9,000 P9.00
      vi Above 9,000 to 10,000 P8.40
      vii Above 10,000 to 15,000 P7.20
      viii Above 15,000 to 20,000 P6.60
      ix Above 20,000 to 30,000 P6.00
      x Above 30,000 P5.00

      NOTE:Computation of the building fee in item 3.d. follows the example of Section 3.c. of this Schedule.

    8. Division J-2 structures shall be assessed 50% of the rate of the principal building of which they are accessories (Sections 3.a. to 3.d.).

  5. Electrical Fees
  6. The following schedule shall be used for computing electrical fees in residential, institutional, commercial and industrial structures:

    1. Total Connected Load (kVA)
    2. Fees
      i 5 kVA or less P200.00
      ii Over 5 kVA to 50 kVA P200.00 + P20.00/kVA
      iii Over 50 kVA to 300 kVA P1,100.00 + P10.00/kVA
      iv Over 300 kVa to 1,500 kVA P3,600.00 + P5.00/kVA
      v Over 1,500 kVA to 6,000 kVA P9,600.00 + P2.50/kVA
      vi Over 6,000 kVA

      P20,850.00 + P1.25/kVAA

      NOTE:Total Connected Load as shown in the load schedule.

    3. Total Transformer/Uninterrupted Power Supply (UPS)/Generator Capacity (kVA)
    4. Fees
      i 5 kVA or less P40.00
      ii Over 5 kVA to 50 kVA P40.00 + P4.00/kVA
      iii Over 50 kVA to 300 kVA P220.00 + P2.00/kVA
      iv Over 300 kVa to 1,500 kVA P720.00 + P1.00/kVA
      v Over 1,500 kVA to 6,000 kVA P1,920.00 + P0.50/kVA
      vi Over 6,000 kVA

      P4,170.00 + P0.25/kVA
      Area in square meters Fee per square meter
      i Original complete construction up to 20.00 sq. meters P3.00
      ii Additional/renovation/alteration up to 20.00 sq. meters regardless of floor area of original construction P3.40
      iii Above 20.00 sq. meters to 50.00 sq. meters P5.20
      iv Above 50.00 sq. meters to 100.00 sq. meters P8.00
      v Above 150.00 sq. meters P8.40

      NOTE:Total Transformer/UPS/Generator Capacity shall include all transformer, UPS and generators which are owned/installed by the owner/applicant as shown in the electrical plans and specifications.

    5. Pole/Attachment Location Plan Permit
    6. i Power Supply Pole Location P30.00/pole
      ii Guying Attachment P30.00/attachment

      This applies to designs/installations within the premises.

    7. Miscellaneous Fees: Electric Meter for union separation, alteration, reconnection or relocation and issuance of Wiring Permit:
    8. Use or Character of
      Occupancy
      Electric Meter Wiring Permit
      Issuance
      Residential P15.00 P15.00
      Commercial/Industrial P60.00 P36.00
      Institutional P30.00 P12.00

    9. Formula for Computation of Fees
    10. The Total Electrical Fees shall be the sum of Sections 4.a. to 4.d. of this Rule.

    11. Formula for Computation of Fees
    12. If the electrical work or installation is found not in conformity with the minimum safety requirements of the Philippine Electrical Codes and the Electrical Engineering Law (RA 7920), and the Owner fails to perform corrective actions within the reasonable time provided by the Building Official, the latter and/or their duly authorized representative shall forthwith cancel the permit and the fees thereon shall be forfeited.

  7. Mechanical Fees
    1. Refrigeration, Air Conditioning and Mechanical Ventilation:
    2. i Refrigeration (cold storage), per ton or fraction thereof P40.00
      ii Ice Plants, per ton or fraction thereof P60.00
      iii Packaged/Centralized Air Conditioning Systems:
      Up to 100 tons, per ton
      P90.00
      iv Every ton or fraction thereof above 100 tons P40.00
      v Window type air conditioners, per unit P60.00
      vi Mechanical Ventilation, per kW or fraction thereof
      of blower or fan, or metric equivalent
      P40.00
      vii In a series of AC/REF systems located in one
      establishment, the total installed tons of refrigeration shall be used as the basis of computation for purposes
      of installation/inspection fees, and shall not be considered
      individually.

      For evaluation purposes:

      For Commercial/Industrial Refrigeration without Ice Making (refer to 5.a.i.):

      1.10 kW per ton, for compressors up to 5 tons capacity.
      1.00 kW per ton, for compressors above 5 tons up to 50 tons capacity.
      0.97 kW per ton, for compressors above 50 tons capacity.

      For Ice making (refer to 5.a.ii.):

      3.50 kW per ton, for compressors up to 50 tons capacity.
      3.25 kW per ton, for compressors above 5 up to 50 tons capacity.
      3.00 kW per ton, for compressors above 50 tons capacity.

      For Air conditioning (refer to 5.a.iii.):

      0.90 kW per ton, for compressors 1.2 to 5 tons capacity.
      0.80 kW per ton, for above 5 up to 50 tons capacity.
      0.70 kW per ton, for compressors above 50 tons capacity.

    3. Escalators and Moving Walks, funiculars and the like:
    4. i Escalator and moving walk, per kW or fraction thereof P10.00
      ii Escalator and moving walks up to to 20.00 lineal meters
      or fraction thereof
      P20.00
      iii Every lineal meter or fraction thereof in excess of 20.00 lineal meters P10.00
      iv Funicular, per kW or fraction thereof P200.00
      (a) Per lineal meter travel P20.00
      v Window type air conditioners, per unit P40.00
      (a) Per lineal meter travel P5.00

    5. Elevators, per unit:
    6. i Motor driven dumbwaiters P600.00
      ii Construction elevators for material P2,000.00
      iii Passenger elevators P5,000.00
      iv Freight elevators P5,000.00
      v Car elevators P5,000.00

    7. Boilers, per kW:
    8. i Up to 7.5 kW P500.00
      ii Above 7.5 kW to 22 kW P700.00
      iii Above 22 kW to 37 kW P900.00
      iv Above 37 kW to 52 kW P1,200.00
      v Above 52 kW to 67 kW P1,400.00
      vi Above 67 kW to 74 kW P1,600.00
      vii Every kW or fraction thereof above 74 kW P5.00

      NOTE:

      1. Boiler rating shall be computed on the basis of 1.00 sq. meter of heating surface for one (1) boiler kW.
      2. Steam from this boiler used to propel any prime-mover is exempted from fees
      3. Steam engines/turbines/etc. propelled from geothermal source will use the same schedule of fees above.

    9. Pressurized water heaters, per unit – P200.00
    10. Water, sump and sewage pumps for commercial/industrial use, per kW or fraction thereof – P60.00
    11. Automatic fire sprinkler system, per sprinkler head – P4.00
    12. Diesel/Gasoline ICE, Steam, Gas Turbine/Engine, Hydro, Nuclear or solar Generating Units and the like, per kW:
    13. i Every kW up to 50 kW P25.00
      ii Above 50 kW up to 100 kW P20.00
      iii Every kW above 100 kW P3.00

    14. Compressed Air, Vacuum, Commercial,
      Institutional and/or Industrial Gases, per outlet – P20.00
    15. Gas Meter, per unit – P100.00
    16. Power piping for gas/steam/etc., per lineal meter
      or fraction thereof or per cu. meter or fraction thereof whichever is higher – P4.00
    17. Other Internal Combustion Engines, including
      cranes, forklifts, loaders, pumps, mixers, compressors
      and the like, not registered with the LTO, per kW:
    18. i Up to 50 kW P10.00
      ii Above 50 kW to 100 kW P12.00
      iii Every above 100 kW or fraction thereof P3.00

    19. Pressure Vessels, per cu. meter or fraction thereof – P60.00
    20. Other Machinery/Equipment for commercial/Industrial/Institutional Use not elsewhere specified,per kW or fraction thereof – P60.00
    21. Pneumatic tubes, Conveyors, Monorails for materials handling and addition to existing supply and/or exhaust duct works and the like, per lineal metes or fraction thereof – P10.00
    22. Weighing Scale Structure, per ton or fraction thereof – P50.00
    23. NOTE:Transfer of machine/equipment location within a building requires a mechanical permit and payment of fees.